CSGOLD Upgrade

65%

Status

Monitoring & Controlling [Testing and Validation of Requirements]

65% complete, updated on Thu 1/2/25 1:32 PM by Joseph Aguilar

Changed Status from Planning to Monitoring & Controlling.
The OIT App Admins & Integration Team had been working with the vendor on Integration testing on 12/09. Checking with the team if that testing was successful and if we can close out the project. or is the Integration testing rescheduled for some time next week.

Details

Dates
Fri 9/20/24 - Fri 1/31/25
Acct/Dept
Office of Information Technology
Type
Solutions Project Management / Default
Health
Green - On track
Created
Fri 9/20/24 1:40 PM
Modified
Fri 1/3/25 4:30 PM

Project Request Form

Requestor
This is an individual that is listed as the person asking for a project evaluation, may not necessarily be the Project Champion.
Ester Bodnar
Project Champion Supervisor
Project Champion's direct Supervisor
Carrie Bernal
Vice Chancellor
Project Champion's Vice Chancellor for the division
Dale Bundy
Requested Delivery Date
Enter an estimated date you would like this project completed/delivered
11/29/2024
List your primary requirements for this solution.
Please list your primary requirements for this solution.
Perform necessary tasks in order to prepare for the CSGOLD upgrade.
Please list any subject matter experts who can assist with this project.
Who has the knowledge in your area or other areas that can assist?
Josue Silva
Sharon Veselka

Description

This project will be used to track and assign tasks related to the CSGOLD upgrade.
All tasks must be completed prior to the 11/14/24 meeting with the vendor.

Manager

Alternate Manager(s)